Ohio Power Siting Board Gives Conditional Approval for Electric Transmission Line Projects in Harrison and Tuscarawas Counties

On May 4, 2017, the Ohio Power Siting Board issued an opinion, order and conditional certificates for AEP Ohio Transmission Company for two electric transmission line projects in Harrison and Tuscarawas Counties known as the Dennison-Yager 138 kilovolt transmission line rebuild project and the Yager-Desert Road 138 kilovolt transmission line rebuild project. The Power Siting Board gave its conditional approval to the projects.

If you have questions regarding this potential project, or your rights, please contact Tom Fusonie (614.464.8261 or thfusonie@vorys.com) or Joe Miller (614.464.6233 or jrmiller@vorys.com).